Sources and Uses of Funds During Construction

  Total Cost
in 2002 Dollars
(in thousands)
Total Cost Inflated Through Construction Year 2010
 
Vehicle
244,868
 
Propulsion System
487,086
 
Energy Supply (ES)
47,350
 
Operation Control System
97,659
 
Infrastructure Control System
4,270
 
Guide way Infrastructure
1,694,553
 
Stations
396,082
 
Operations & Maintenance Facilities
68,430
 
Corridor Infrastructure
126,494
 
Construction & Procurement Costs
3,166,792
 
     
Right-of-Way
92,000
 
Soft Costs
482,400
 
Total Construction Related Costs
3,741,192
4,361,483
Finance Related Costs:  
623,495
Total Uses of Funds / Project Costs  
4,984,978
     
     
Sources of Funds:    
Current Interest Revenue Bonds (CIB)
38.7%
1,927,950
Capital Appreciation Revenue Bonds (CAB)
18.7%
932,738
TIFIA
10.7%
534,421
Federal Grant
19.1%
950,000
Other Grants
11.0%
550,000
Interest Earnings
1.8%
89,869
Total Sources of Funds  
4,984,978

 

Operating and Maintenance Costs for the Baltimore-Washington Maglev Project (in 2002 dollars)

Salaries
Quantity

Cost

Managers

25
$2,530,600

Maintenance of Operating System

4
$408,800

Other

28
$1,962,500
Subtotal Salaries
57
$4,901,900
     
Wages
Quantity
Cost

Operation Control Center

19
$1,413,000

Propulsion/Energy System

14
$1,034,700

Guideway

10
$735,000

Fixed Facilities

6
$433,100

Vehicle

33
$2,380,600

Dispatcher

5
$390,500

Spare Parts

6
$396,800

Product Support

6
$451,200

Vehicle Preparation and Operation

35
$2,099,700

Stations

60
$3,446,200
Subtotal Wages
194
$12,780,800
     
Non-Personnel
Quantity
Cost

Utility Cost

 
$9,419,200

AFC Parts (per 1000 Riders)

9,170,000
$91,800

Mobile Equipment

1
$819,500

Vehicle (Section) Maint Materials (each)

21
$5,048,100

Propulsion system

3
$441,700

Energy Supply

3
$363,200

Operation Control System

64.8
$1,134,300

Guideway Materials

64.8
$602,600

Operations Control Center

1
$437,100

Management Support/Docs/Training

1
$284,100

Stations

3
$479,500

Insurance

 
$2,084,500
Subtotal Non-personnel  
$21,205,600
Fixed Costs  
$1,897,900
     
Subtotal Costs  
$40,786,000
     
Contingency  
$12,236,000
     
Total Costs  
$53,022,000