HomeContact UsSite MapSearch
The Baltimore-Washington Maglev Project
About the Project
Environmental Impact Statement
Technology
Public Involvement
Public/Private Partnerships
FAQs
Links
Maglev Train
Project Overview
within this section: Project Overview | Project Team Members
Project Timeline
| Benefits & Future Connections
Project Timeline
October, 1998 TEA-21 enacted; establishes Maglev Deployment Program
   
February, 1999 Application submitted to Federal Railroad Administration (FRA) for Baltimore-Washington project
   
May, 1999 U.S. Department of Transportation Secretary Rodney Slater announces selection of seven project corridors to receive funds for pre-construction planning such as engineering feasibility and environmental studies.
   
July, 1999 Maryland Transit Administration (MTA), in cooperation with Washington, D.C., Baltimore City and Baltimore County, begins environmental assessment and project description of Baltimore-Washington corridor project.
   
October, 1999 Public information meetings held in Baltimore City, Washington, D.C., and Anne Arundel County.
   
October, 1999 – February, 2000 Ongoing study evaluating analysis, alignments and environmental impacts.
   
February, 2000 Environmental assessment submitted to Federal Railroad Administration (FRA) on February 29, 2000.
   
April, 2000 Public information meetings held in Baltimore City, Washington, D.C., and Prince George’s County.
   
June, 2000 FRA completed Draft Programmatic Environmental Impact Statement (PEIS) of seven corridor projects.
   
June, 2000 Project Description submitted to FRA
   
August, 2000 FRA and MTA hosted a public information meeting for the Draft Programmatic EIS in Baltimore.
   
January, 2001 U.S. Department of Transportation Secretary Rodney Slater announces Baltimore-Washington corridor project is one of two project corridors to be considered for further funding study.
   
July, 2001 MTA initiates Draft EIS and Preliminary Engineering work
   
Fall 2001 Industry roundtables to encourage formation of private sector teams to design, build, operate, maintain the system, furnish technology components and develop stations. Study group to consider ownership legislation.
   
March, 2002 MTA holds public workshops on three alternative alignments
   
Spring, 2002 General Assembly considers legislation to establish task force to recommend entity to develop, own and operate project
   
October, 2002 – February, 2003 Task Force meets; makes recommendations to Governor, General Assembly
   
October, 2002 Alternatives Analysis portion of EIS complete; MTA holds community meetings to review detailed findings regarding impacts
   
September, 2003 Draft EIS completed; submitted to FRA
   
December 2003 FRA holds public hearings on DEIS; single “preferred” alignment selected
   
October, 2003 – March, 2004 TEA-21 Reauthorization (project must be reauthorized to continue to receive federal funds) Federal Funds secured.
   
Summer, 2004 Final EIS completed; final hearing held.
   
Fall, 2004 Record of Decision (ROD) issued.
   
Winter, 2004 Maryland General Assembly approval of the design, construction and funding. New legislation to establish entity to develop, own and operate project
   
2004 - 2005 Actions to place local project funding in Consolidated Transportation Program and Metropolitan Transportation Improvement Program
   
2004 - 2005 Prepare Bid Documents, geotechnical investigations, plans to 30% completion
   
2005 Non-Federal budget appropriations
   
2005 Project revenue bonds secured
   
2005 - 2006 Procurement of a Design/Build team
Design preparation and Right-of-way acquisition
   
2006 - 2009 Construction of guideway, facilities and stations
   
2009 - 2010 Safety testing and certification
   
2010, 2011 Revenue service begins
   
Note: All future dates assume preceding steps completed on schedule.

 

   return to top